The Queensland Curtis LNG project
successfully transported the first gas from the Surat Basin coal seam
gas fields onto Curtis Island, Australia, where a liquefaction terminal
is located. QGC, the wholly owned Australian subsidiary of BG Group, is
developing the Queensland Curtis LNG (QCLNG) Project, the world’s first
project to turn coal seam gas into LNG.
Arrival
of first gas onto the island enables commissioning work to begin on the
first of two LNG production trains being developed by BG Group. This
commissioning work is expected to begin in the first quarter of 2014.

Commenting
on the milestone, BG Group chief executive Chris Finlayson said:
“Delivering this key milestone demonstrates the advanced stage of
development at the world’s first coal seam gas to LNG project. We are
now entering the final construction and commissioning phases and we
remain firmly on track to deliver first commercial LNG in the second
half of 2014, as scheduled and within the US$20.4 billion budget.”
QCLNG is
one of Australia’s largest capital infrastructure projects. Delivery of
first gas onto the island marks the successful completion of a two-year
task to lay more than 46,000 lengths of one-metre diameter steel pipe
over 540 kilometres – the longest large-diameter buried pipeline in
Australia. The site on Curtis Island can accommodate an expansion to 12
million tonnes of LNG a year, subject to demand.